Scrivener Dam, impounds the Molonglo River to form Canberra’s iconic Lake Burley Griffin. The lake constitutes one of Canberra’s key landscape features in accordance with Walter Burley Griffin’s vision for the city.
Construction of the dam commenced in 1960 and was completed in 1964. During the dams 2011 annual safety and surveillance inspection, corrosion to the original anchor bolts was discovered, resulting in a proposal to install new anchorage to each of the gate hinges. The Scrivener Dam Anchor Bolt Remediation project involved the replacement of 120 gate hinge anchor bolts across the Dam’s overflow ‘fish-belly’ flap gates with 60 modern equivalents.
The new 6m anchors were installed to 0mm in 3000mm straightness and 1mm in 500mm direction/ alignment tolerance. Core drilling operations were particularly complex due to overhead constraints in the work areas. Each core barrel required splicing in 1.2m lengths, introducing a weakness into the core barrel with potential to affect straightness and alignment.
The project was delivered on time and significantly below initial budget expectations
Let us know how we can help, get in touch via the form below.
We’re constantly on the lookout for new talent. If you like what you see and want to join our team, fill out the form below and we’ll get back to you as soon as we can.